Published by Todd Bush on September 18, 2025
Dow Inc.’s flagship blue hydrogen-based chemicals complex in Alberta, Canada, will be delayed by up to two years amid market weakness.
Jim Fitterling, CEO, confirmed the delay to its Path2Zero project, originally announced in April, could last between one and two years until market conditions improve, pushing back what had been billed as a showcase for hydrogen in chemicals decarbonisation.
The $11.5bn Path2Zero project plans to expand Dow’s ethylene and polyethylene capacity in Fort Saskatchewan while cutting around 1.5 million tonnes of annual carbon dioxide emissions.
>> In Other News: Patented Innovation Allows Affordable Long-Range Detection of CO2 Leaks at Underground Storage Sites and Pipelines
At the heart of Path2Zero is a large-scale blue hydrogen facility, designed to fuel Dow’s new ethylene cracker and existing operations in place of natural gas. Built and operated by Linde, the plant will combine hydrogen production with carbon capture and storage.
Phase one of the development was due in 2027 before expanding in 2029.
However, the firm delayed construction of the development, citing concerns over global economic conditions and the impact of US tariffs. As a result of the delay, Fitterling said it would save $1bn in 2025 capital spend.
“The plan was to bring it up in ’27,” the CEO told investors. “In this market environment, that doesn’t feel like the right timing.
“We’ve announced a one-year delay. I think a one- to two-year delay timeframe is what we’re looking at.”
Fitterling said that the delay would allow Dow to balance continuing engineering work and order long-lead equipment while holding off on major construction works until it is ready to commit.
But the delay will have an impact on hydrogen supply. Linde announced it would invest over $2bn to build, own, and operate a large-scale blue hydrogen and atmospheric gases production facility to support the development.
Initially, Linde downplayed the delay to remain firm on its $7bn in sale-of-gas project pipeline, pointing to contract protections in place for delays caused by customers.
Fitterling stressed that Dow had “good ongoing dialogue” with the industrial gas major to manage engineering and labour “hand in glove.”
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue 🏭 Global CCS Hits 113 Projects as Americas Lead Capacity 💰 We're Moving $2M+ to Climate Solutions 💧 China Launches World's First Semi-submersible Offshore Wind-to-hydrogen Platfo...
Inside This Issue 🪨 Inside Blm's 650,000-Acre Bet on Wyoming Carbon Storage 🏭 California Advances Carbon Capture and Removal Regulations Under SB 905 ⚡ Why a Japanese Power Giant Is Betting on Den...
Inside This Issue ⚖️ Colorado Takes Over Class VI Permits: What Changes for CCS? 🏭 Hebei Shoulang Facility Using LanzaTech Technology Achieves World’s First ISCC EU RCF Certification for Ethanol P...
A consortium led by Novacium, together with Axel’One and AD-VENTA, has secured funding from the Defence Innovation Agency (AID) and the Directorate General of Armaments (DGA) under the RAPID progr...
Video: The Next Chapter https://youtu.be/LUIHqS35rMg Led by John Douglas, whose development experience includes the $8 billion Champlain Hudson Power Express, the collaboration brings major Nort...
Emvolon Raises $22 Million Funding Round to Launch Its Modular, Waste-to-Fuel Chemical Plants
Following its recent offtake agreement and increased commercial demand, Emvolon raises Series A and non-dilutive federal and state grants to launch first commercial system and adds industry growth ...
Puro.earth Expands DACCS Certification With CCS+ Methodologies
Puro.earth has published its CCS+ methodology documents, with direct air capture and geological storage (DACCS) as the first activity type implemented under its CCS+ Program. Puro.earth’s multi-pr...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.