Texas is taking significant steps to enhance its carbon capture and storage (CCS) efforts. Congressmen August Pfluger and Dan Crenshaw have urged the Environmental Protection Agency (EPA) to expedite the Texas Railroad Commission's (RRC) application for primary enforcement authority—known as "primacy"—over Class VI underground injection control wells. These wells are essential for the geologic sequestration of carbon dioxide (CO₂), a critical component in reducing greenhouse gas emissions.
Class VI wells are specifically designed for the injection of CO₂ into deep rock formations for long-term storage, a process known as geologic sequestration. This method aims to prevent CO₂ from entering the atmosphere, thereby mitigating climate change.
>> RELATED: Texas's Carbon Gamble: Will Storage Solutions Spark Growth or Disaster?
The EPA currently faces a substantial backlog in processing Class VI well permit applications. As of recent reports, the agency had received 159 applications, with only a few permits issued.
The goal is to review complete applications and issue permits within approximately 24 months; however, this timeline is influenced by factors such as project complexity and application completeness.
This delay has significant implications for CCS projects nationwide. Permitting bottlenecks hinder the timely deployment of essential carbon sequestration infrastructure, which is vital for achieving emission reduction targets. The backlog also affects investor confidence and the overall momentum of climate initiatives.
In response to these delays, several states have sought primacy to manage their own Class VI well permitting processes. Texas formally submitted its application for primacy on December 19, 2022. Granting the RRC this authority would allow for a more streamlined and efficient permitting process, leveraging the state's extensive experience with its unique geology and existing infrastructure.
Allowing the RRC to oversee Class VI well permitting offers several advantages:
Enhanced Efficiency: State-level management can reduce bureaucratic delays, leading to faster project approvals.
Local Expertise: The RRC's deep understanding of Texas's geological formations ensures that permits are evaluated with the highest level of technical proficiency.
Economic Growth: Expedited permitting can attract more CCS projects to Texas, fostering job creation and economic development in the energy sector.
Texas is not alone in seeking primacy for Class VI well permitting. As of February 2025, the EPA has granted primacy to four states: North Dakota, Wyoming, Louisiana, and most recently, West Virginia. This move aims to expedite approvals and advance the development of large-scale carbon sequestration projects.
Despite these advancements, Texas's application for primacy remains under EPA review. The state's energy and industrial sectors are keenly awaiting approval, as Texas currently has 43 CCS projects under review—accounting for a significant portion of all U.S. applications.
Zack Abnet, Texas State Director for the American Conservation Coalition, emphasized the state's leadership in energy innovation, noting, "When it comes to energy, you can always count on Texas’ innovative spirit and get-it-done attitude to lead the way."

>> In Other News: Aramco Slashes Blue Ammonia Output to Reduce Costs
Several factors contribute to the delays in Class VI well permitting:
Resource Constraints: The EPA has faced challenges in hiring sufficient technical staff to manage the increasing number of applications.
Complex Regulations: The intricate nature of CCS projects requires comprehensive evaluations to ensure environmental safety, prolonging the review process.
Public Participation: Engaging with local communities and addressing environmental justice concerns add layers of complexity to the permitting timeline.
The delays have prompted responses from both industry stakeholders and legislators. In April 2024, the bipartisan Climate Solutions Caucus sent a letter to the EPA expressing concern over the slow pace of Class VI well permitting and state primacy approvals.
The caucus expressed concern over the slow pace of Class VI well permitting, stating, "Permitting delays are actively crippling U.S. efforts to deploy vital clean energy and carbon capture infrastructure alike."
The RRC has been proactive in positioning itself to take on the responsibility of Class VI well permitting. In May 2022, the commission approved the submission of a pre-application for Class VI primacy to the EPA and requested that the governor formally seek EPA approval. Subsequently, in August 2022, the RRC adopted amended rules to align with federal regulations, demonstrating its readiness to implement a Class VI UIC program.
Achieving primacy is a critical step for Texas to accelerate its CCS initiatives. With the state's vast industrial base and geological capacity for CO₂ storage, streamlined permitting could position Texas as a leader in carbon sequestration. This advancement would not only contribute to national climate goals but also bolster the state's economy by attracting investment in cutting-edge energy projects.
The collaboration between Texas lawmakers and the RRC underscores the state's commitment to advancing carbon capture technologies. By seeking state oversight through primacy, Texas aims to streamline processes, leverage local expertise, and play a significant role in reducing carbon emissions. The timely approval of the RRC's application by the EPA is crucial for the state's CCS ambitions and could serve as a model for other states navigating similar challenges.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue 💧 Blue Hydrogen Just Won 2025: 10x More Than Green ✈️ Houston American Energy Advances Development of Sustainable Aviation Fuel ⛏️ Max Power Expands Natural Hydrogen Discovery Po...
Inside This Issue ⚡ Google's Power Play: First CCS Deal Reshapes Energy 🌎 True North Carbon's Tamarack Project, Canada's Largest Single-Technology Direct Air Capture Deployment, Achieves First Cap...
Inside This Issue 💰 The $27/ton Question: What Makes a Carbon Removal Credit Worth 3x More? 🛢️ EPA Issues Three Class VI Permits to ExxonMobil in Jefferson County, Texas 🌍 UN Endorses First Articl...
BILBAO, Spain — H2SITE, the deep-tech start-up revolutionizing high-purity hydrogen production through cutting-edge palladium membrane technology, is scaling up its industrial presence with project...
CCS+ Initiative and Puro.earth Join Forces to Integrate Carbon Credit Methodologies and Scale CCS
Today, the CCS+ Initiative and Puro.earth (Puro), a leading standard and registry for durable carbon removal, announced that they have signed a Memorandum of Understanding (MoU). Through this strat...
October 27, 2025 Company to supply critical compression equipment for ammonia production and CO2 transportation, and a steam turbine-driven power generation generator technology Facility to produ...
BUFFALO, N.Y., Oct. 27, 2025 /PRNewswire/ -- Buffalo Biodiesel Inc., a leading recycler of used cooking oil (UCO) and a pioneer in renewable feedstock production, recently announced that it has suc...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.