Construction at the Woodfibre LNG site continues to progress steadily. Recent milestones include ongoing foundation work for LNG processing equipment and the arrival of the first pipe rack modules in May.
Current site activities include backfilling, grading, concrete pours, rock scaling, and advancement of onshore casings for the floating storage tank mooring structures. Erosion and sediment control measures, along with environmental best practices, remain fully implemented and monitored.
>> In Other News: Honeywell, Johnson Matthey, Gidara Energy and Samsung E&A Form SAF Technology Alliance

Pipe racks arriving on site
In preparation for module deliveries and the upcoming in-water construction window, spill prevention and response drills have been conducted. Additional training will be delivered by the Western Canada Marine Response Corporation (WCMRC) for all contractors involved in marine activities. Environmental monitoring and mitigation measures continue in response to evolving site conditions and construction scopes. Daily bird monitoring and amphibian exclusion and salvage operations are conducted under the direction of a Qualified Environmental Professional. A full-time wildlife monitor is also in place to manage bear activity, ensuring the safety of both wildlife and workers. All construction activity is paused when bears approach active work areas, resuming only after they leave naturally and are out of harm’s way.

M02 foundation
The project has a noise exemption variance permit in place from the District of Squamish as some works are required to continue past noise bylaw hours. Night work will continue over the coming months, including form work, concrete pours and site maintenance, including erosion and sediment control. Noise monitoring at Britannia and Squamish harbour continues.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue ✈️ Par Pacific's Kapolei Biorefinery Is Now Making SAF in Hawaii ⛽ IRFA Confident Year-Round E15 Will Receive Strong, Bipartisan Support During May 13 House Vote 🛩️ LanzaTech Sel...
Inside This Issue ⚙️ Horizon's 5MW AEM Delivery to Rockcheck Steel Marks a Commercial First 🗺️ Verra Selects Data Service Providers to Produce REDD Risk Maps 🟢 More Green Hydrogen on Its Way 🔌 Ten...
Inside This Issue 🌬️ California Commits $11 Million To Advance Direct Air Capture Demonstration Projects 🤝 Colorado And Wyoming Sign Agreement To Coordinate Carbon Storage Permitting 🧪 Deep Tech S...
MUNICH, May 11, 2026 /PRNewswire/ -- At IFAT Munich 2026, Vary Tech, a global leader in solid waste resource utilization, together with Evonik and SupeZET, officially launched a full-industry chain...
Greenlane Signs Definitive Agreements With Panasonic As Cascade LF Production Partner In Brazil
~Partnership establishes local production facility to fulfill Brazilian demand for Greenlane's next-generation landfill gas upgrading technology~ VANCOUVER, BC, May 11, 2026 /CNW/ - Greenlane Rene...
Fusion Fuel Announces BioSteam Energy Has Begun Commercial Operations
Majority-Owned Joint Venture Begins Biomass-Powered Steam Operations at Dairy Facility in South Africa, With Right of First Refusal on Future Projects Dublin, May 11, 2026 (GLOBE NEWSWIRE) -- Fusi...
€500 Million Project Targets 79 000 Tonnes of Sustainable Aviation Fuel and 9 000 Tonnes of Renewable Diesel Annually GHENT, Belgium, May 11, 2026 (GLOBE NEWSWIRE) -- North Sea Port is delighted t...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.