Construction at the Woodfibre LNG site continues to progress steadily. Recent milestones include ongoing foundation work for LNG processing equipment and the arrival of the first pipe rack modules in May.
Current site activities include backfilling, grading, concrete pours, rock scaling, and advancement of onshore casings for the floating storage tank mooring structures. Erosion and sediment control measures, along with environmental best practices, remain fully implemented and monitored.
>> In Other News: Honeywell, Johnson Matthey, Gidara Energy and Samsung E&A Form SAF Technology Alliance

Pipe racks arriving on site
In preparation for module deliveries and the upcoming in-water construction window, spill prevention and response drills have been conducted. Additional training will be delivered by the Western Canada Marine Response Corporation (WCMRC) for all contractors involved in marine activities. Environmental monitoring and mitigation measures continue in response to evolving site conditions and construction scopes. Daily bird monitoring and amphibian exclusion and salvage operations are conducted under the direction of a Qualified Environmental Professional. A full-time wildlife monitor is also in place to manage bear activity, ensuring the safety of both wildlife and workers. All construction activity is paused when bears approach active work areas, resuming only after they leave naturally and are out of harm’s way.

M02 foundation
The project has a noise exemption variance permit in place from the District of Squamish as some works are required to continue past noise bylaw hours. Night work will continue over the coming months, including form work, concrete pours and site maintenance, including erosion and sediment control. Noise monitoring at Britannia and Squamish harbour continues.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue ⚡️ Florida Just Made Hydrogen History With This First 🏗️ KBR Awarded FEED for Coastal Bend LNG Project 🌱 Grassroots Carbon Becomes First U.S. Company to Deliver 1.9 Million Tons ...
Inside This Issue 💧 Duke Energy Florida Unveils Nation's First System Capable Of Producing, Storing And Combusting 100% Green Hydrogen ✈️ Technip Energies’ Hummingbird Technology Powers LanzaJet’s...
Inside This Issue 💰 The $9B Deal That Almost Didn't Happen ⚖️ IMO Rules Understate Benefits of Utilising Captured Carbon, Says GCMD 🌾 Corteva and bp Launch Biofuel Feedstock Joint Venture Etlas 🔬 ...
Milkywire Completes Pre-Purchases to Accelerate Next-Generation Carbon Removal
Milkywire has completed Salesforce-backed pre-purchases of over 12,500 tonnes of durable carbon removal from 19 suppliers, spanning six carbon removal methods and 15 countries. The purchases were ...
Uniper CEO Michael Lewis: "One of the first large-scale supply corridors between India and Europe" AM Green Founder Anil Kumar Chalamalasetty: "A milestone for India's role in the global energy tr...
As part of its regenerative ranching program, Grassroots Carbon has paid $40 million to its ranching partners across the United States San Antonio, TX, Jan. 09, 2026 (GLOBE NEWSWIRE) -- Grassroots...
KBR Awarded FEED for Coastal Bend LNG Project
HOUSTON, Jan. 12, 2026 (GLOBE NEWSWIRE) -- KBR (NYSE: KBR) has been awarded the front-end engineering design (FEED) contract for Coastal Bend LNG’s planned natural gas liquefaction and export facil...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.