Construction at the Woodfibre LNG site continues to progress steadily. Recent milestones include ongoing foundation work for LNG processing equipment and the arrival of the first pipe rack modules in May.
Current site activities include backfilling, grading, concrete pours, rock scaling, and advancement of onshore casings for the floating storage tank mooring structures. Erosion and sediment control measures, along with environmental best practices, remain fully implemented and monitored.
>> In Other News: Honeywell, Johnson Matthey, Gidara Energy and Samsung E&A Form SAF Technology Alliance

Pipe racks arriving on site
In preparation for module deliveries and the upcoming in-water construction window, spill prevention and response drills have been conducted. Additional training will be delivered by the Western Canada Marine Response Corporation (WCMRC) for all contractors involved in marine activities. Environmental monitoring and mitigation measures continue in response to evolving site conditions and construction scopes. Daily bird monitoring and amphibian exclusion and salvage operations are conducted under the direction of a Qualified Environmental Professional. A full-time wildlife monitor is also in place to manage bear activity, ensuring the safety of both wildlife and workers. All construction activity is paused when bears approach active work areas, resuming only after they leave naturally and are out of harm’s way.

M02 foundation
The project has a noise exemption variance permit in place from the District of Squamish as some works are required to continue past noise bylaw hours. Night work will continue over the coming months, including form work, concrete pours and site maintenance, including erosion and sediment control. Noise monitoring at Britannia and Squamish harbour continues.
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.
Inside This Issue 🏗️ Louisiana Blocks Parish CCS Bans to Protect $20B Pipeline ⛽ Hyperfuels and Terra Mater Form Strategic Partnership on Low-Carbon Fuel 🌿 Skytree Announces First Commercial Skytr...
Inside This Issue 🧠 Enchant Energy Offers a Carbon Answer to America's Surging AI Data Center Demand 🌊 Carbon Dioxide Removal Will Need to Scale Faster Than Solar to Meet Climate Targets 🌱 Graphyt...
Inside This Issue ✈️ AIRCO's Pennsylvania Hub Makes Jet Fuel from CO2 On-Site 🛡️ Initial Partners Selected in Air Force Geologic Hydrogen Energy Resilience Initiative 🍁 Alberta Releases Updated Qu...
“K” LINE Secures Time Charter Contract Of Newly Built Liquefied CO2 Carrier For Northern Lights
Kawasaki Kisen Kaisha, Ltd. (“K” LINE) is pleased to announce that, jointly with Malaysia-based MISC Berhad (MISC), it has secured a time charter contract for a newly built 12,000 m3 liquefied CO2 ...
The Global Cement and Concrete Association (GCCA) and the Global CCS Institute are delighted to announce the signing of a Memorandum of Understanding (MOU). The agreement establishes a framework be...
AMSTERDAM, June 03, 2026 — Skytree, a leader in modular onsite Direct Air Capture (DAC) technology, and Lingezegen Energy, a regional Dutch energy company serving greenhouses, announce their partne...
GRAND FALLS-WINDSOR, Newfoundland and Labrador, June 05, 2026 (GLOBE NEWSWIRE) -- [First Atlantic Nickel & Cobalt Corp.](https://www.fanickel.com/) (TSXV: FAN | OTCQB: FANCF | FSE: P21) ("Firs...
Follow the money flow of climate, technology, and energy investments to uncover new opportunities and jobs.